TCN Gives Update As Blackout Hits Nigeria In Latest National Grid Collapse

Date: 07-11-2024 9:20 pm (4 weeks ago) | Author: onuigbo felicia
- at 7-11-2024 09:20 PM (4 weeks ago)
(f)

The Transmission Company of Nigeria (TCN) has shared the reason for Thursday morning’s national grid collapse.

Recall Nigeria’s weak electricity grid system collapsed again on Thursday, barely 24 hours after a committee set up by the Federal Government to end the national power grid incessant collapses submitted its report.

The collapse, the second time this week and the 10th in 2024 left the country without public power supply with power generation and distribution companies taking huge financial hits and customers expressing frustrations.

Data from the National System Operator showed that the grid, which had been recovering from the collapse that occurred on October 6th, had peaked at 4,360.8MW on Wednesday with the lowest generation at 1,454.64MW.

The NSO data indicated that the grid supplied 2,709.45MW as of 11am yesterday but dropped dramatically to 4.5MW at 12pm with only Afam VI (3.7MW) and Omoku (0.8MW) power plants on the grid.

It however began a gradual recovery at 1pm reaching 104.8MW with Azura IPP (91MW) back on the grid.

In an update on the latest power supply setback, the Transmission Company of Nigeria, TCN, attributed it to “a sudden rise in frequency from 50.33Hz to 51.44Hz”.

TCN General Manager, Public Affairs, Ndidi Mbah said recovery efforts were ongoing to restore the grid.

“TCN wishes to inform the public that the national grid experienced a disturbance at approximately 11:29 AM this morning, caused by a sudden rise in frequency from 50.33Hz to 51.44Hz. Recovery efforts began immediately, and the Abuja Axis was restored within 28 minutes. Recovery is still ongoing.

“The frequency spike was caused by issues encountered at one of TCN’s substations, which had to be shut down to prevent further complications. In addition to this, we are actively engaged in significant repair work on several critical transmission lines and substations. This includes the 330kV transmission lines along the Shiroro–Mando axis, major upgrades at the Jebba Transmission Substation, and the restoration of the second Ugwuaji–Apir 330kV transmission line.

“Furthermore, following the submission of the investigative report on the causes of previous grid collapses, we have begun addressing the identified weaknesses in the transmission system. Efforts are being made to close the gaps highlighted in the report, and to enhance the overall stability and resilience of the grid. These efforts include both technical upgrades and strategic interventions based on the committee’s recommendations.

“However, it is important to note that while these repairs and improvements are underway, some degree of instability in the system is likely to persist until all major works are completed. We acknowledge the impact of these disruptions and ask for the understanding and patience of the public during this challenging period.

“TCN remains committed to improving the reliability of electricity supply, recognizing the vital role that stable power plays in Nigeria’s socio-economic development. We assure the public that all necessary measures are being taken to ensure the grid’s long-term stability, in line with the recommendations of the investigative committee, while also addressing infrastructure damage such as vandalized transmission lines”,
she stated.

Speaking on the issue of incessant grid collapses, the President, Chartered Institute of Power Engineers of Nigeria, CIPEN, Engr. Israel Abraham blamed politics involved in making decisions on where to site grid infrastructure as well as poor maintenance culture for the current grid challenges.

Engr. Abraham noted that significant investment is needed to replace the old lines and networks before the grid would stabilize.

“The grid is a connection from generation to transmission to distribution and up to the consumer where you are. It involves all the wires and networks. It is the connection of interconnections of all these equipment and accessories. Most of this equipment are aged and need to be replaced. You need to reconduct the lines because they have been there for decades.

“To reconduct the lines means you have to remove the old ones and put in new ones or you upgrade it from maybe a lower capacity to a higher one. These things are necessary because as the population grows, you have more people taking power in certain areas and you need to reconduct or you need to upgrade such facilities”
.

He pointed out that the location of most substations across the country was not driven by expert decisions but politically made with equipment sited at locations where they are not needed causing imbalance in the system

“And if you now have a situation whereby you are not in control to do what you need to do, I go back to that same word again of patronage, you find that you just do what you are asked to do. And if you do what you are asked to do, then you will have what you should have.

“But if we can actually take charge completely and you have professionals deciding what to do, then some of these things will gradually fade out because we will be able to make professional decisions. For instance, in this very environment where we are right now, maybe they need a transformer that is just maybe 500 kVA.

“But if the owner of this place is politically savvy, he can force the government or pass through some politicians and they will bring it in as a constituency project and put maybe a one-megawatt transformer. Now, what happens is the rest is wasted and it also has a negative impact on the grid system”.


He urged the Federal Government to summon the political will and ensure that the right things are done in the sector, and also permanently end the culture of political patronage in the execution of projects in the power sector.

Meanwhile, the Minister of Power, Chief Adebayo Adelabu has ordered the immediate implementation of the recommendations made by the panel that investigated the causes of grid collapses in the country.

Chief Adelabu in a statement by his Special Adviser on Media, Mr. Bolaji Tunji said that all relevant agencies in the ministry must brace up for the immediate implementation of the recommendations of the committee.

“The recommendations of the committee are far-reaching and will proffer lasting solutions to the incessant power grid collapses that we have embarrassingly witnessed in the country in the immediate and long term”, Bolaji said.

Speaking to Vanguard, a top official in one of the leading power generation companies lamented that GENCOS have incurred huge losses since frequent collapses began last month.

The official who did not wish to be named for fear of victimisation said: “If you know how much we have lost commercially you won’t be asking that question and that is not counting the damages done to our machines by the frequent shutdowns.

“Who will pay for the damages? TCN? FG that owes us so much? NERC? NBET? I can tell you that the industry is in a precarious situation and it would collapse if nothing is done urgently to arrest these failures”,
the source stated.

Posted: at 7-11-2024 09:20 PM (4 weeks ago) | Addicted Hero
- kp45 at 8-11-2024 06:58 AM (4 weeks ago)
(m)
The are using it to cash out.
Posted: at 8-11-2024 06:58 AM (4 weeks ago) | Addicted Hero
Reply

Featured Discussions