Africa:Kenya\Uganda Oil Pipeline Project at Stake

Date: 29-04-2011 2:05 pm (13 years ago) | Author: Solomon
- at 29-04-2011 02:05 PM (13 years ago)
(m)

Political instability in Libya is beginning to take a heavy toll on the progress of the Kenya Uganda oil pipeline — one of the most critical regional infrastructure projects in East Africa.

Correspondence seen by The EastAfrican shows that Kenya and Uganda have now insisted that they will delay any equity injection into the joint venture with Libya’s Tamoil East Africa Ltd until after the project has taken off the ground.

The two governments have also demanded that the Libyans pay off landowners along the way leave of the project.

When the parties first signed a Heads of Agreement in January 2007, the understanding was that Kenya and Uganda would each inject 12.5 per cent in equity into the company.

It was also agreed that the two East African countries would contribute land on the way leave as part of their equity contribution.

In Kenya, the Ministry of Lands has released the compensation schedules for parcels of land along the project’s way-leave to be acquired through easements and outright land acquisition.

The submitted schedule contains about 2,107 formally and informally subdivided plots with an estimated total compensation cost of Ksh520 million ($6.19 million).

The tough conditions given to the Libyans by Nairobi and Kampala are a reflection of growing impatience about a project that was supposed to have been commissioned more than three years ago.

/2011/04/28/africakenyauganda-oil-pipeline-project-at-stake/

Posted: at 29-04-2011 02:05 PM (13 years ago) | Newbie
- giftmurphy at 30-04-2011 10:47 AM (13 years ago)
(f)
 Undecided
Posted: at 30-04-2011 10:47 AM (13 years ago) | Hero
Reply