The revelations are quite disturbing. Continue to see more:
Fencing of schools – N200M ($1.3M) in 2012, N200M ($1.3M) in 2011 and N150M ($1M) in 2010. In all schools visited no fencing exists at most you see very old fences, not constructed by any of them.
At Chief Melford Okilo Memorial Hospital – N1.4B ($8.8M) was budget in 2012, N6B ($37.5M) in 2011, N415M ($2.6M) in 2010, N3.5B ($22M) in 2009. The project has been completed but abandoned and non-functional.
Completion of on-going health facilities- N350M ($2.2M) was budgeted in 2012, N986M ($6.2M) in 2011 but no facility was completed in 2012 or 2011.
Construction and renovation of General Hospitals- N1.8B ($12M) was budgeted in 2012 on visit to the general hospital Sagbama, no renovation has taken place- here is a photo.
At the General Hospital Ogbia, the facility has stopped being a hospital out of neglect, being rented out as apartment, even though its been budgeted for by the state government.
Fencing and Landscaping of “School-to-Land Authority” Premises – N45m ($280K) was budgeted and nothing was done. The facility is currently abandoned.
Bayelsa State Rice Training and Seed Multiplication center – N150M ($1M) was budgeted, site is abandoned and no work done.
Construction of veterinary clinic and provision of equipment at Edepie – N100M ($625K) was budget in 2012, N60m ($375K) in 2010, and N100M ($625k) in 2009. No construction done at all.
Construction and Development of storage facilities of aquaculture center at Edepie – N300M ($1.9M) was budgeted in 2012 at the project site no construction was done.
Home Economics Center at St. Jude Girls Secondary school Amarata – N11.7M ($73K) was budgeted in 2012, but the existing facility no longer exists as the dilapidated infrastructure has been taken over by the police: see photo below:
Construction of 3 Senatorial Model Secondary Schools in Nembe, Sagbama & Yenagoa; N2billion ($12.5M) was budgeted in 2012; N1.4billion ($8.75M) in 2011; N2billion ($12.5M) in 2010
At Yenago site of project, 80% completion recorded, but was being used as a flood relief camp when we visited.
In Sagbama, the site was covered by flood, but community said no work had begun.
At Nembe site work was just 10 percent, but had since stopped. Nothing was done in 2012
Medical equipment for health centres: N300million ($1.9M) was budgeted. At Kaiama Comprehensive Health Center, last supply was 2010.
Medical equipment for health centres: N300million ($1.9M) was budgeted. At Sagbama Comprehensive Health Center, last supply was 2010
Medical equipment for health centres: N300million ($1.9M) Comprehensive Heath Nembe. No supply was made.
sourcewww.olokunbolablessing.blogspot.com